Hybrid Construction Cost per m² in Croatia: What the Benchmark Means and How the Price Is Fixed

Cost is usually the first question an investor or developer asks about hybrid construction, and the right one. This article explains the indicative cost per m² for a MODULUXE hybrid building in Croatia, Slovenia and Montenegro, why the number is a benchmark rather than a quote, and how the fixed price for your project is confirmed.

It expands on the answer to "How does the cost compare to traditional concrete builds?" in our Common Questions.

Illustrative hybrid building on the Adriatic coast
Illustration. Not a completed MODULUXE project.

The indicative benchmark: €2,000–€3,200 per m²*

Our indicative turnkey benchmark for hybrid construction is €2,000–€3,200 per m²*.

Two points matter when you read that range:

  • It is indicative. It helps you test a budget at concept stage. It is not a quotation and not a fixed rate per m².
  • It excludes VAT (PDV). VAT treatment depends on who the buyer is and how the contract is structured, so take advice from your own tax adviser.

*All listed turnkey CapEx prices are indicative and exclude VAT (PDV).

How your fixed price is set: at the end of the design phase

The per-m² range gets you to a first conversation. The number you sign is different: your fixed price is confirmed at the end of the design phase, under a single design-and-build contract.

This works because one team handles design, permit documentation, executive drawings and construction. Your building is designed for timber, concrete and steel from the first sketch, so the estimate at design stage and the final cost stay aligned. Nothing has to be redesigned later to suit a separate builder.

Illustrative example. An investor briefs us with a €10M budget. After the design phase we confirm €9.2M. That is the contract price.

Read more: Why Design & Build gives you the price you were quoted.

Illustrative example. Not an actual project.

What you bring to the first meeting

To design to your budget, we start from your parameters:

  1. Plot – location, size and constraints.
  2. Target budget – the figure the project has to work within.
  3. Programme – for example, the number of apartments or the office area you need.

How hybrid construction compares with a traditional all-concrete build

A traditional all-concrete build and a MODULUXE hybrid building both use concrete. In our buildings, concrete cores carry the main structural stability, while cross-laminated timber (CLT) floors and walls and glulam columns make up the primary material by volume. The cost comparison is therefore less about materials and more about how the project is procured and delivered.

QuestionTypical split-contract routeMODULUXE Design & Build
Who designs and who builds?Separate architect and contractorOne accountable team
When is the price known?Price often changes after tenderFixed price confirmed at the end of the design phase
Benchmark used at concept stageVaries by project€2,000–€3,200/m²* indicative

*All listed turnkey CapEx prices are indicative and exclude VAT (PDV).

It can cost more at first glance

Hybrid construction can cost more at first glance. Faster delivery, cost certainty and lower energy use can make it the more economical choice over the life of the project.

That is why we suggest comparing total cost of ownership, not only the construction price per m².

Three factors that affect the total cost of a project

1. Construction finance

A faster build shortens the period you carry construction finance, which reduces interest cost. Illustrative. Depends on your financing terms.

2. Usable floor area

Timber walls are slimmer than masonry, so the same footprint can hold more usable space. On one plan we drew twice, the same 86 m² ground floor has 67.5 m² of net usable area in reinforced concrete and 71.1 m² in CLT: 3.6 m² more. The external wall is 29.2 cm in CLT against 37.7 cm, 8.5 cm slimmer.

The same 86 m² ground floor drawn twice: reinforced-concrete walls on the left, CLT walls on the right, with net usable floor area for each room
Example on one plan. The gain is calculated for each design.

Example on one plan. The gain is calculated for each design.

See how slimmer walls add usable space.

External wall thickness to scale: reinforced-concrete wall 37.7 cm and CLT wall 29.2 cm, with wall layers
Example on one plan. The gain is calculated for each design.

3. Budget certainty

A single design-and-build contract, with one team from permit to handover, reduces budget creep and keeps estimate and final cost aligned.

Can I use my own architect?

Yes. If you already work with an architect, we recommend involving our team before the design is final, so the building is optimised for hybrid construction from the start. That protects the alignment between the design-stage estimate and the price you pay.

FAQ

How much does hybrid construction cost per m² in Croatia?

Our indicative turnkey benchmark is €2,000–€3,200 per m²*. Your fixed price is confirmed at the end of the design phase.

*All listed turnkey CapEx prices are indicative and exclude VAT (PDV).

Does the per-m² price include VAT?

No. The benchmark excludes VAT (PDV). Please consult your own tax adviser on VAT for your project.

When do I get a fixed price?

At the end of the design phase, under a single design-and-build contract.

Is hybrid construction more expensive than a traditional build?

It can cost more at first glance. Faster delivery, cost certainty and lower energy use can make it the more economical choice over the life of the project.

Can I use my own architect?

Yes. We recommend involving our team before the design is final, so it is optimised for hybrid construction from the start.

Next step

Send us your plot, target budget and programme. We will tell you how a hybrid building could work within them, and what the design phase involves.

Talk to our team

Planning a building in Croatia, Slovenia or Montenegro?

Tell us about the site and the building. We will talk through the design, the structure and the questions above before you commit to anything.

Contact MODULUXE

© 2026 MODULUXE d.o.o. · Kovinska 28, 10000 Zagreb, Croatia

Disclaimer: The information on this website is general and indicative. It is not a binding offer, quotation or professional advice. Prices, timelines, savings and performance figures depend on the project and are confirmed in writing in the design phase and in the contract. Images, renders and visualisations are illustrative, may be AI-generated, and may not show completed MODULUXE projects. Tax and VAT information is for information only; please consult your own advisers. Third-party names and logos belong to their owners and do not imply endorsement. We are not responsible for the content of external websites.